plan order basic finish date in the past/not coincidence with open date

emmayoung
Participant
0 Kudos
504

hi everyone

I ran into an werid issue when MRP planning. 

the Ind requirement is in the future 2024/09/10, but the corresponding planning order geneated basic finish date is fall into past date 2023/11/20. for the planned item, it's in-house days is set to zero.  when I run MRP calculation, the parameter is 3-create plann order,3-Schedule lines, 1- create MRP list, 3-delete and recreate planning data. so every time the planning order should be re-generated.

无标题.png

for this generated plan order, only the opending date is correct. we need to align to the opening date!

无标题2.png

the requirement is attached to a network. I checked the network dates, and it is also correct.

无标题3.png

BTW, because this project created in system is an old one, I modifed the start date and end date in project to apply to newly attached component requirements(PIR) for test.

I dont' know how this happen.. please give some guidance, thanks in advance.

 

Accepted Solutions (1)

Accepted Solutions (1)

DominikTylczyn
SAP Champion
SAP Champion

Hello @emmayoung 

Are you sure you have replanned MRP after you have changed the project dates?

Try to run regenerative MRP for the material in question. That should rebuild procurement proposals irrespective of MRP file entries.

Best regards

Dominik Tylczynski

emmayoung
Participant
hi Dominik, thanks for your kindly reply on this issue. Sure, I have regenerate MRP planning after I changed project dates and save it. It seemed there is some cache impact on the MRP result. Since it is in a test enviroment, so I created a new project and attach the same assembly material with same requirement date, the planned order dates(including opening dates, basic start/end dates) turns into correct now.