Dear Community,

I understand same issue were reported in past and there are multiple blogs are available. 

However, none of the blogs are helping to fix my issue.

I am doing CK11N for Subcontracting material and getting error message of 'CK 468 No price could be determined for subcontracting'.

I have checked below list of activities:

- Price strategy under Subcontracting tab of valuation variant is 4 (Gross Quotation Price), 7 (Net Purchase Order Price) and 5 (Effective Price from Quotation)

- Material master is maintained with procurement type 'X' and Special Procurement as '30'

- Purchasing Info record is maintained with valid vendor and validity period and no deletion flag is set

- Purchase order also exist for same material and vendor against PIR

- Material master is also checked in MRP, Purchasing, Accounting and Costing view. Field for 'Do Not Cost' is unticked

Despite of all above mentioned activities, I am getting subject mentioned issue. Also, there are more than 20 subcontracting material but only material is working correctly while rest materials are giving error.

Only difference I noticed between failed vs correct data is value in 'Price Strategy' column in CK11N itemization is blank for failed data while it is appearing as '7' for correct data.  However, I am unable to figure out why price strategy is blank. 

SAP S/4HANA Cloud Public Edition  FIN Controlling  

 

View Entire Topic
OwenLiu
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello,

It's mentioned in the KBA

Remove the External Processing selection from the Routing if no longer applicable.

Have you tried the same?

If the same still can't solve the issue, suggest you create customer case.

Best Regards,
Owen

Virendrafico_87
Discoverer
0 Kudos

Hi Owen,

Thanks for your reply.

However, I am getting subject mentioned error while running standard costing for Subcontracting material wherein we have BoM only and no routing for the same. Hence, not sure if mentioned solution of 'Remove the External Processing selection from the Routing if no longer applicable' is relevant for this issue.

Also, I checked mentioned setting in routing for main material wherein subcontracting material is component for production material and it's already unticked.

 

Regards,