on ‎2019 Aug 11 8:51 AM
Dear Experts
in FM for 2019 the budget carry forward was done successfully but about 4 months later we get errors while posting PO and PR that says we dont have sufficient budget and we saw that some commitment items have become negative.but we have 3 cases,suppose we want to post a po for 20$.
1-if the commitment is 0 or more than zero the system issues the error and says we need 20$.
2-if the commitment is negative the system says we need 15700$!! which is not even then negative amount+ Po amount. I mean there is no relation between them.
please kindly advice me of what maybe wrong with budget or budget carry forward.
Request clarification before answering.
Hi,
First of all, I suggest you to initialize your AVC ledger, as the symptoms you describe suggest that it might be in disorder. After doing so (via FMAVCREINIT), please, report if the problem persists.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 8 | |
| 7 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.