Hi Experts,

In this scenario, since data related to loan has been entered in SAP as on 01, Apr 2021. Total tenure is for 10 years for first 7 years it was on moratorium, on 8th year loan has been paid 30% (Principle+ Interest), 2021, April is the 9th year we have entered the opening as XXX after deducting 30%.
Customer require to have old historic data for entire moratorium period.
Please advise.

Thanks & Regards,
Suresh P

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Here you can use zero condition in conditions tab for that period

0 Kudos

Here you can use zero condition in conditions tab for that period

0 Kudos

Here you can use zero condition in conditions tab for that period