Modify Package

former_member599120
Contributor
0 Kudos
83

Dear Experts,

I know SAP BPC has default data managers package, likes export data and full optimize. I would like to join 2 tasks to be one package, is it fine? Could you please advise me how to customize package, BPC will run full optimize task first and then export data task?

I really appreciate your help. Please help me

Thank you for your information.

Kind Regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Package links is the option. On Full Optimize, if you refer to any of the SAP notes on full optimize, SAP advises not to run this package unless advised by their support team. Just thought of altering you on that.

You could have light optimize included if you want to compress the requests and if you also want to delete records with zero signed data.

Thanks,

Sreeni

Former Member
0 Kudos

Hi,

In BPC NW, you have the concept of package links. These are used to club together multiple packages. When you execute the package link, it will execute the underlying package.

Hope this helps.