on ‎2016 Nov 23 5:55 AM
Hello,
when trying to mitigate to risk from risk analysis, We are unable to see the controls associated with risk.
Getting Message as "For Org rule analysis when performing mitigation from the risk analysis report do not mitigate the user from management summary report , only user summary or detail view to mitigate the risk".
However we are mitigating risk in Summary or detail view only.
Kindly suggest.
Thanks,
Lakshmi
Request clarification before answering.
Ken/Lakshmi,
please share your current support pack level and a screenshot of the issue. That will help to identify your issue.
Cheers, Alessandro
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lakshmi, I have the same issue. Did you find a solution that you could share?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 15 | |
| 11 | |
| 10 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.