on ‎2017 Jan 06 10:55 AM
Dear Expert,
while carry forward the open commitment ( SC/PO ) we are getting the below error message.
FMKU083:The budget amount is not sufficient for release
Kindly check attached herewith FMJ2 error massage & FMAVCR01 budget Status
All consumable budget( 70,593,642.00)are already released at time upload the budget..
When we enter normal budget(unreleased budget) in this commitment item equal to carry carry forward open budget that time this error is not coming.
Appreciated for your reply to fix this issue
Thanks
Request clarification before answering.
Hi,
Please, consult OSS note 1859520 - Budget release in BCS. Make sure that document types used in carry-forward process (I guess, you carry-over the budget with the commitment) are duly defined to work with automatic release.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 41 | |
| 4 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.