Hello experts,

I am using in BPC embedded, the option master data planning on the fly, but my issues is that I cannot switch planning mode on/off from the process chain, in BW4/Hana I can switch on/off planning mode only in ADSOs.

Can anyone give me an idea to solve my issue?

Best Regards,

Cristina

Accepted Solutions (1)

Accepted Solutions (1)

gregor_dieckmann
Product and Topic Expert
Product and Topic Expert

Hi Cristina,

in transaction RSPC you can model a process chain to switch a planning enabled master data InfoProvider to 'load or planning mode' in the same way as for aDSOs.

Regards,

Gregor

Answers (1)

Answers (1)

0 Likes

Hi Gregor,

Thank you for the help.

You are right, from RSPC is stil working.