on 2019 Jul 19 8:02 PM
Hello All,
We are using a program : FARR_PERIOD_IN_CLOSING (T.Code: FARR_PERIOD_IN_CLOSING) to change the status from Open to in close for RAR Periods.
We have scheduled a batch job with list of co.codes in the variant. When we execute this job, system took only first co.code in the variant and ignoring other co.codes in the variant and job shows as finished.
Could you please suggest, if there is any solution to consider all the co.codes in the variant.
Thanks in Advance.
A.Prasad
Hello All,
We were able to find the workaround for this issue. Initially, we used to give co.codes individually in the co.code field, then system is considering the first co.code only in the list and ignoring the remaining co.codes.
To handle this issue, we are updating co.codes as a range ex : 1090 to 1099 / 2000-2100 / 3000-3100 etc., in the respective jobs.
Hope this information is helpful for you to handle the issue.
Thanks & Regards,
A.Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
14 | |
4 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.