2024 Mar 14 2:58 PM - edited 2024 Mar 18 1:41 AM
1743460 - Compound Interest with different method calculation bases - SAP for Me
Trying to implement Compound interest as listed in the note above in S/4 system; updating entries into the tables is not helping.
Created a transaction using T.Code "FTR_CREATE" with Variable Rate using formula to determine Interest Percentage, Settles and ran Interest Rate Adjustment.
Pmnt Amount 117,996.53 for 50,000,000.00 does not match with percentage rate 1.80%; expected 900,000.
1.80% - Variable rate - Determined using a formula.
Please let me know how to resolve these.
Thank You for your time.
Request clarification before answering.
Issue Resolved ..
50000000 * Percentage Rate/100 * <Working Days>/252
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.