on 2015 Aug 06 4:41 PM
Hallo All,
I have done the complete set up for Inward Processing but I do not find the inbound
delivery in work-list
The steps I am following to create Inward Processing are – Create Open Transit
(generate MRN - NCTS) in GTS, Create Purchase Order and created Inbound
Delivery (Update Preliminary Document type T1 and the Movement Reference Number
from Open NCTS), transfer order (Warehouse) and Good Receipt.
If I am not wrong it should appear in Enter Customs Declaration after Goods
Receipt but it is not picking up for IPR.
Kindl suggest or advice to figure out where I am missing.
Thanks,
Madhu
Request clarification before answering.
Hi Madhu,
Do you mean that the GR is not appearing at all (even for free-circulation), or that is IS appearing for import to free-circulation but not for import to IPR?
Thanks for that clarification.
Regards,
Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hallo Dave,
Thank you!
Yes I am not able to see the documents in the work list for import declaration after goods receipt for both free circulation as well as the IPR process.
For free circulation here are the steps I followed,
•Opened an NCTS Procedure
•Created PO and inbound delivery in the feeder system
•Added the Preliminary doc type and the MRN number in the inbound delivery (At this point I’m not sure if the process is to close the NCTS procedure before we do the receipt to do import declaration)
•Discharged the transit procedure using the Customs shipment document in the transit area of the import side. Document moved to the presentation area (At this stage the import declaration can be created as a follow up from the Presentation but somehow I am not able to do that either)
So my question is at what stage the document should appear in the Worklist? and I’m not sure if I am missing any configuration or any some BADI’S that might prevent this.
Also we are not able to create the import declaration as a follow up to the presentation?
Before doing the goods receipt I was able to see the documents in the “worklist prior to goods receipt”.
Thanks,
Madhu
Hi Madhu,
I am getting old, it's true, but you don't need to write quite so big .
The GTS side normally starts when you enter the MRN and save the Inbound Delivery - that action should create a Customs Shipment in GTS, allowing you to close the NCTS procedure.
At any time after the Customs Shipment has been created, your Goods Receipt posting (from VL32N, MIGO or MB01) should appear in the work-list for Customs Declarations after GR.
If that's not happening, then you should re-check your configuration - I'm sure you've got the Configuration Guide to hand. Don't worry about the IPR aspect at this stage; just work with the free-circulation work-list, which covers all receipts.
Regards,
Dave
Hi Madhu,
Don't worry - I was referring only to the font size, not the content!
If you have not coded any BAdIs, then you don't need to check them. Otherwise check in the BAdIs /SAPSLL/CTRL_MM0C_R3 and /SAPSLL/IFEX_MM0C_R3 to make sure that nothing is preventing transfer of the Goods Receipt posting.
Regards,
Dave
Hi Saitsh,
Yes I see the documents under the transaction /N /SAPSLL/CUOR04_IMP (Display Existing Import Documents) but not in work list. Also I see the doucments in Program /SAPSLL/CIBD_WL_DISPLAY (Display Shipping Notificcations). The documents are passed to GTS but not sure why they are not appearing in worklist.
Thanks,
Madhu
Hi Madhu,
Right from the start of this thread, you keep talking as if the Inbound Delivery (IBD) should appear in the work-list for creating Customs Declarations after Goods Receipt. To be quite clear, that work-list contains Goods Receipt (Material Document) items, not IBDs.
Generally speaking, GR items are only transferred to the work-list if:
Regarding that last point, I'm wondering about the fact that your IBD are transferring as CIBD. Maybe you could look at the header entry for one of them (table /SAPSLL/CUHD) using Transaction SE16, and check the value of field CDCUS. If it is set to 'X', then that would prevent the GR transferring to the work-list.
Otherwise, please check the configuration for your IBD type in the feeder system (table /SAPSLL/TLER3B), and let us know how the fields are set in that entry.
Regards,
Dave
Hallo Dave,
Thank you.
Yes, the material documents are not appearng in worklist to create Import declaration.
I have created new documents with new material and I do not see them in work list (even for free-circulation). Also checked the configuraton and see the preliminary document type mapping looks OK.
Not sure what is causing.
Thanks,
Madhu
Hi Dave,
Due to technical issues I could not check the steps suggeted by you. Now I can see in table /SAPSLL/CUHD field value for CDCUS (Customs service) is set with "X" but initially it was blank. The entry for LECCUS in table /SAPSLL/TLECHS exists. Am I missing something in customization.
Thanks in advance.
Regards,
Madhu
Hi
Have you: create a Customs id, have you assigned a combination of plant sloc to it in both ECC and GTS?
Have you assigned this plant/sloc to a specific IPR legal unit?
Have you assinged your products in GTS to this Customs id under IPR; have you retransfer back this info to ECC?
have you set the activity sequence for IPR accordingly ?
you need to check all the IPR settings are done.
KInd regards
Assen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Madhu -
Did you activate your document and setup the communication processes under Customs Management?
Rachael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 11 | |
| 9 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.