on 2021 Jan 03 5:15 PM
Our client what’s to implement fund management at plant level for existing company code.
Business has 6 different company codes. same chart account and controlling area also common for all company code.
Business has several plants for company code. client decided to implement a fund management for only one plant. is that possible to implement fund management for particular plant. it should not affect other plant or company code.
Does it’s possible to use existing g/l master?
Any impact for existing Asset master and coast center. Profit center...etc.
Derivation rule able set at plant level.
System info sap s/4 hana 1609
Thanks and Regards
kiran,s
Request clarification before answering.
Hi,
PSM-FM is activated on Financial Management (FM) area, which is linked to company code(s). So, FM is not activated on plant level. However, you can play with FM derivation rules and apply budgetary control only to a specific plant represented by FM assignment object, say, Fund centre. Other objects can be made exempt from availability control or even FM documents posting.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 8 | |
| 7 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.