on 2024 Jul 08 5:17 PM
In case of WBS-Element result analysis calculation for previous period, I am getting below warning message and system calculates COS instead of work in process. Please someone explain if the attached configuration screen has any link to determine COS/WIP calculation for previous and current period. As my expectation was to calculate WIP for previous period and COS for current period but it always calculate COS for previous period.
Note: As of now, final RA field is blank in our case.
Message no. KJ355
The Final RA indicator is set in the valuation method for the current status of the results analysis object. The method for manual results analysis was therefore set to E (manual change).
The next time results analysis is performed, the system will cancel the values entered manually in closed periods.
Check the valuation method if necessary.
Request clarification before answering.