I am calculating result analysis for WBS Element and getting below warning.

sandeep_boina
Newcomer
0 Kudos
209

In case of WBS-Element result analysis calculation for previous period,RA Config (1).PNG I am getting below warning message and system calculates COS instead of work in process. Please someone explain if the attached configuration screen has any link to determine COS/WIP calculation for previous and current period. As my expectation was to calculate WIP for previous period and COS for current period but it always calculate COS for previous period.

Note: As of now, final RA field is blank in our case.

Manual results anlaysis set to "E"

Message no. KJ355

Diagnosis

The Final RA indicator is set in the valuation method for the current status of the results analysis object. The method for manual results analysis was therefore set to E (manual change).

System Response

The next time results analysis is performed, the system will cancel the values entered manually in closed periods.

Procedure

Check the valuation method if necessary.