on ‎2018 Aug 09 6:42 AM
Hi
I am working on GR in SAP and having an issue with PO Number which is locked and I am not able to proceed further with Goods Receipt. Please help me out.
Thanks and Regards
Vivek Rajagopalan
Request clarification before answering.
Vivek, the standard SAP GTS compliance check does not block Goods Receipt. Just to check, what message are you getting. Does it indicate anything related to SAP GTS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I suppose that you have Delivery completed indicator checked for the items. So you get the error message, through which you can go in debug change the deliv.inidcator into unchecked and that save and create GR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 8 | |
| 7 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.