GTS checks against PP and PS

former_member256034
Participant
0 Likes
401

Hi All,

has anybody an idea how we can do compliance checks against our production order components (PP) and network activity components (PS). Due to business requirements we are considering to expand our checks against those document types, too.

Best regards,

Carsten

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member194424
Active Participant
0 Likes

Hello Carsten,

There is no direct GTS integration with PS (I don't think there is one with PP either). What I can instead suggest is creating outbound project deliveries (using transaction CNS0) for the project/WBS element. The project generates the demand and outbound delivery is created against the WBS element. Once the outbound delivery has been created, GTS checks occur as they do on outbound deliveries. Remember to maintain pricing in the outbound delivery for GTS purposes.

Regards,

Satish