on 2024 Jul 10 11:52 AM
Hi Experts
I have configured Fund Management for client. When I post PR or PO the system demands Fund, Fund Centre and Commitment Item. The system however does not check budget limit and allows me to post documents without information/warning/error message.
Client requirement is the system should check budget availability from PR/PO stage
Please let me know how to do it
Rajeev Uppal
Request clarification before answering.
Check transaction code OF37 for PR/PO and OF39 for Statistical update