on 2019 Aug 28 12:34 PM
Dear team,
We are using ECC 617 0010.
We are facing a issue in Budget consumption report. After analysis we found that, the value type 50 (Purchase requisition) amount was not reduced with amount type 200 after the creation of subsequent purchase order. Because of which, system consuming double the budget and not releasing consumption amount from Purchase requisition.
Please advice.
Many Thanks
Request clarification before answering.
Hi,
If it is SES, as I suspected, there could be different reasons for this discrepancy. It is complicated to find the reason without looking into the system. Raise OSS ticket, unless you can debug the system by yourself.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the case of Service PR , The difference between the PR and PO will be in the Rem Ord Plan(blocking the Budget) , if the PR value is Higher.
Kindly TECO the Service Activity in which the PR is created. This works in Project Systems
Alternatively you can modify the PR value to same as the PO Value.
Unfortunately it does not take the PO value as commitment and Ignore the PR value in case of Service PR's
Regards,
Shareeq
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, this bug was only with SES PR's.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It could be a bug or a temporary glitch. What kind of PR is it? Is it SES?
Did you try to run FMN3N?
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 7 | |
| 7 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.