on 2025 Apr 15 11:05 AM
Hi Experts,
I do have one question.
In Event Based Product Costing, Actual Overheads are getting charged immediately on to Production Order if we have maintained Actual OH Rate / Percentage in Costing Sheet OH Rates.
Where as in Actual Business Condition, Determination of Actual OH Rate is only possible after Period End Closing. How to handle this?
How to allocate actual incurred overheads on to product during Actual Costing??
I have gone through Actual Costing 33Q, Event Based Product Costing (3F0) Processes, but I could not find the answer.
Please guide me in this scenario.
Thanks in Advance
Nitin
Request clarification before answering.
Hi Nitin,
You can use this job template:
Postprocess Event-Based Postings - Overhead Calculation | SAP Help Portal
Best Regards,
Owen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
9 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.