on 2019 Jul 24 3:36 PM
Hi All.
We are having a issue with budget control check.
We have a purchase order with service line item with a amount of 457.779,54BRL.
Despite its still having more then 156.320,37BRL of budget commitment, when we try to enter a Service Entry Sheet(ML81N) with a total amount of 43.023,60BRL, system show us a message of Budget exceed(FMAVC 005).
We´ve had already tried to change the item data to update de commitment, but this do not worked
Anyone could sugest something?
Regards.
Leonardo
Request clarification before answering.
| User | Count |
|---|---|
| 8 | |
| 8 | |
| 7 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.