on 2019 Apr 10 7:17 PM
I ran a standard cost in march and released and ran the standard costs again yesterday for the same materials. Now I wanted to delete yesterday’s costing which is now the correct standard costs for the materials- how do I go about doing that on CKR1 without deleting March standard costs
I have tried to specify the valid from day by putting yesterday date but SAP still pull in March.
And I do not want to delete March.
Request clarification before answering.