Hi GTS experts,

I activated the document tranfer to GTS and did all the customizing for document types and item etc. for SPL and Embargo.

First problem is that no automatic transfer to GTS takes place. Second problem, when I do the tranfer via PlugIn the log states that the item would already be completed and no Screening was done.

/SAPSLL/ITREC is empty.

Does anybody screen the purchase agreements?

Thanks and best regards,

Carsten

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member256034
Participant
0 Likes

Thanks, but it is already in the system.

former_member194424
Active Participant
0 Likes

Hello Carsten,

Please check OSS note 1570856, I had the same problem. Upon applying this note, it was resolved.