Hello SAP Community,
Would like to get your insights on how these two apps (Cost Center Budget Report and Project Budget Report) are working in S4 Hana Public Cloud. We tried to open the app and display the uploaded Plan Amount in Import Financial Data app but it is not showing any balances. But when we checked P/L Plan/Actual Report, the data can be displayed.
Thank you,
Marife
Request clarification before answering.
Hi Marife,
The 2 apps are with different logic of getting data.
For Project Budget Report, please check KBA:
2799100 - Fiori app 'Project Cost Report' / 'Project Budget Report' shows zero costs
For Cost Center Budget Report, make sure you use G/L account hierarchies which are created in app Manage Global Hierarchies, as the account group in SSCUI 102781 Maintain Budget Availability Control Profile for Cost Centers
Best Regards,
Owen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.