on 2025 Apr 07 12:37 PM
Dear Community,
it is possible to change or delete wrong created overhead rates? We created our own overhead rate but we set the wrong Dependency.
Request clarification before answering.
Hi,
just to add to what my colleague already said: it is sadly not possible to delete your overhead rate P200 itself and a change of the dependency is also not possible after creation. If you want to have a custom overhead rate with another dependency, you have to delete all entries for P200 in the costing sheet and recreate a new one with the correct dependency.
Best regards
Marvin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
9 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.