2 weeks ago
Dear Team,
for certain companies it will be required for us to have dunning letters.
It will be for 3 companies.
Would it be please possible to set up a meeting with You to check the process together?
Thank You.
Best regards,
Request clarification before answering.
Hello,
Hope you are doing well.
In regards to dunning implementation (or any other consulting questions), we have documents from the help portal that can help you on this regard. They provide guidance on how to set up the configuration and use the functionality.
You can start with: Automatic Dunning:
A snippet from it:
"Prerequisites
You have made the following settings:
Scoping
You have entered the country-specific dunning procedures.
Fine-Tuning
You have defined the dunning strategy in the Business Configuration work center under Activity List Fine-Tune Cash Flow Management.
You can specify the dunning strategies that the system should use when creating a dunning proposal list. These settings determine when the overdue items are included.
Master Data
In the Application and User Management work center, you can select the dunning form you want to use and specify how it should be sent.
Process Flow
Create a Dunning Proposal List
You create the dunning proposal list using the dunning run. For more information, see Quick Guide for Dunning Runs (Receivables)".
Other resources you can use:
Quick Guide for Dunning
Edit and Execute Dunning
Also a blog post: Dunning in SAP Business ByDesign
Best regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.