Budget report for actual commitment for top Managment

sarvottam_tomar
Explorer
0 Kudos
374

Dear All,

we have requirement from business management. they want to budget report for actual commitment. they just want to know where we consumed our budget in PR-PO and invoices. we provide the Zbudget report of standard report FMAVCR01. But they don't want to replicate the documents. Suppose we committed budget on PR then system send the budget on PO and they minus budget on PR document. they want to remove this one also.

Regards

Sarvottam Tomar

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi,

Ok, so your client basically wants to see how much they committed on the budget, and not consumed counting also actuals, which, in many cases, will reduce the commitment consumption. Well, you can use FMRP_RFFMEP1OX report, then. If you want to see it on documents level.

For totals, you can create a user report in report painter based on 4FM library, excluding 0200 amount type (reduction) from the amounts of your commitments (PR,PO).

Regards,

Eli

sarvottam_tomar
Explorer
0 Kudos

Dear Eli,

I tried in FMAVCR01 and total subtotal and filter as per their requirement. i tried to remove 0200 (reduction) but after this my consumed amount total has changed. Now how we can remove the 0 subtotal amount. 2nd screen short only subtotal amount can come with text.

iklovski
Active Contributor
0 Kudos

Obviously it will change, as you remove reductions of your commitments from your consumption. I'm afraid there could be misunderstanding of what your client wants to see, though. Once more, if they want to know how much was committed (without any impact of what out those commitments was invoiced), or they want to see budget consumption (commitments and actuals) all along.