BPC Standard Process chain active with error "no valid start conditions"

jialin_lijialin
Explorer
0 Kudos
435

Dear BPC/BW Gurus,

Good evening. I got an issue when I processed Data manager package. When I create Data manager package with using process chain "/CPMB/APPEND" but it always fail when I load the flat files. I checked the RSA1 AND I found those BPC Process chains are not active version (All in M) and I try to install in BI content or active manually but system report below errors "No valid start conditions". Can anyone give me some comments? Thank you!

Regards

Jialin

The detail error message as below

Accepted Solutions (0)

Answers (4)

Answers (4)

jialin_lijialin
Explorer
0 Kudos

Hi Frank,

I checked the schedule job should not be triggered but I did try and found still not work.


regards

JL

fmnor79
Active Participant
0 Kudos

Update: I see, how about checking settings under "Edit Conditions" button, scheduling should be flagged with "immediately" if process chain should trigger directly after it first was activated.

jialin_lijialin
Explorer
0 Kudos

Hi Frank,

Usually after click immediately, if there will be a schedule job released? I got nothing happened in schedule job.

Regards

Jialin

jialin_lijialin
Explorer
0 Kudos

hi Frank,

Thank you for your reply but our system SP is same as what the SAP notes suggested and the notes already in the system and the issue in the notes also different with mine. Any further comments?


regards

JL

fmnor79
Active Participant
0 Kudos

Hi

regarding "No valid start conditions" (/CPMB/*) during process chain activation. Seem like issue has been addressed with SAP Note 3023704 - Unable to create BPC data package - BPC NW. Resolution: Implement note 2987123 and then run program UJS_ACTIVATE_CONTENT with option "Activate BI Business Content".

Best regards,