BPC Copy function between periods

md_fasi
Participant
693

Hi Team,

I want to use planning sequence copy function to copy the data,below are the example

example

Period 1 to till period 12 of 2000 to

Period 0 20001

When I use in parameter of copy function, the above periods(i.e copying 12 all periods to 1 period of year)

It is not copying I cant see any data transfered in AFO report,

Kindly help.

System details

BW7.4 BPC 10.1

Thanks in advance

Regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi,

While creating copy planning function select 0fiscper in Field to be changed.

In parameter of copy function create two variables for 0fiscper one for source and one for target.

And source variable type should be Range and target variable type can be single value or range.

Then, in AFO when you run planning function give the range of time period in source variable and in target variable give one value of time in which you want to copy data.