on ‎2018 Aug 23 11:35 AM
Hi All,
We have an unique requirement for BoM explosion.
In ECC
BoM created as a Master data and available in MAST table.
But while creating PO and Inbound Delivery, we are not exploding the BoM into the documents. ( we are creating PO/Inb Del with header material only)
In GTS
while transferring PO and Inbound Delivery, we have exploded BoMs and reference Customs Documents created with BoM Components.
PO(No BoM) --> Customs Document (with BoM Components)
Inb (No BoM)-->Customs Document (With Bom Components)
But while generating worklist "Create Cus Decl prior to Goods Receipt" the components are not exploded in the worklist".
I have also created BoP ID and assigned all the components in GTS Product Master data. but still it is not working.
Can you some one help me on this. it is very urgent.
Request clarification before answering.
Hi All,
Country of Dep/Dest are updated same at item level Geography tab in the Customs Document created with ref to Inb Delivery.
Done the modifications in the transfer BADI @ inb del level and worklist generated successfully with components.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 34 | |
| 6 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.