Active Budget Check in S/4 HANA

Former Member
0 Likes
1,412

Is there active Budget check (Funds Management) at GL Account and Cost Center level in S/4 HANA?

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Likes

Hi,

You are mixing the terms. G/L account and cost centre are not the part of FM (Funds Management). The objects for FM are different: fund centres, commitment items, funds, etc. You can indeed create a mapping between G/L accounts and commitment items, and also between cost centres and, say, fund centres. Then, you will introduce your budget in FM and the availability check will also happen in FM, simulating the combination of a G/L account with a cost centre, if this is your goal.

Regards,

Eli

vtr1cob
Participant
0 Likes

eli.klovski ,

I just saw your reply while searching for one of my customer requirement.

While showing the Cost center budget feature in S/4HANA GL account/ groups and Cost centers) , Customer need budget availability check for Cost centers in standard purchase requisitions and purchase orders (Which are not account assigned with category K or F).

This feature is available in Fund Management. My Customer is looking for the similar feature for budget control in Purchase orders and purchase requisition (with account assignment category Blank), but, will provide Cost center and system should check the cost center budget).

Thanks for any import in this process in advance

regards,

Viswanathan T R

iklovski
Active Contributor
0 Likes

I answered on your original question.