on ‎2025 Jun 19 5:24 PM
Hi Experts.
We are experiencing an issue during the settlements from Wbs to Assets.
Our Projects have a structure that allows the Asset be object receiver only in settlement rule for 2nd level wbs element. So whatever is posted in wbs from level 3 to higher is rolled up to level 2. Anyway the Down Payment assigned to level 3,4 or 5 and then rolled up to level 2 cannot be settled to Assets.
Questions:
Is this a SAP Standard depending on GL automating determination during settlements? Is that a SAP Standard Solution to this scenario in SAP ECC or SAP S/4HANA?
Best regards.
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
As i know , Only amount posted to primary cost elements with WBS can be settled.
Please control the CJI3 Report for you WBS
only reported data in this report can be settle
Best Regards
Ghazal Afshar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi;
First off all, check if the lower WBS elements use the same settlement profile as the WBS element that settles to fixed assets. I believe they don’t. Then, check the Allocation Structure to see if the account is Assigned.
Regards
Marcio Blos
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 15 | |
| 11 | |
| 11 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.