2025 WBS Settlement to Assets is failing for Down payments

0 Likes
721

Hi Experts.

We are experiencing an issue during the settlements from Wbs to Assets.

Our Projects have a structure that allows the Asset be object receiver only in settlement rule for 2nd level wbs element. So whatever is posted in wbs from level 3 to higher is rolled up to level 2. Anyway the Down Payment assigned to level 3,4 or 5 and then rolled up to level 2 cannot be settled to Assets.

Questions:

Is this a SAP Standard depending on GL automating determination during settlements? Is that a SAP Standard Solution to this scenario in SAP ECC or SAP S/4HANA?  

Best regards.

Accepted Solutions (0)

Answers (3)

Answers (3)

RaymondGiuseppi
Active Contributor
gafshar_prodea
Explorer
0 Likes

Hello 

As i know , Only amount posted to primary cost elements with WBS can be settled. 

Please control the CJI3 Report for you WBS

only reported data in this report can be settle 

Best Regards

Ghazal Afshar

MarcioBlos
Active Participant
0 Likes

Hi;

First off all, check if the lower WBS elements use the same settlement profile as the WBS element that settles to fixed assets. I believe they don’t. Then, check the Allocation Structure to see if the account is Assigned.

Regards
Marcio Blos

0 Likes
Hi Marcio. Wbs 5 level and 2 level share the same Settlement Profile and Allocation Structure. But only the Level2 is assigned to an Investment Profile that is flagged to Manage "Auc". When I try to roll up Level5 to Level4 no Downpayment is considered.