Business Scenario
Management may have to do Audit on the data coming from / loaded into different applications. In this blog post i will share some of my experience how we did that.
Here we are pushing the FI/CO Actual data from BW Info cubes (Finance, Controlling, Internal Orders,ECCS - Consolidation & Cost Center Accounting) into BPC relevant models which are defined by the Business.
This is to confirm the data we are pushing from BW to BPC is right and so that we can explain to the Internal Audit team if something goes wrong at the data perspective any point of time.AsActual data plays an important role in the BPC side (Budgeting, Forecasting &Planning) and to do various EPM reports in comparing against Actual vs forecast vs plan vs budgeting its a good practice to have a control report to make sure the input data from BW is always right when entering into BPC.
Environment
BW - 7.31 SP 09
CPMBPC - 801 SP 08
BOBJ - 4.0
Assumptions
Below is the design and functional flow of the BW - BPC Control report.
The example below is taken for One Finance Cube from BW and relevant BPC Model .
Tasks
These kind of reports can be developed to compare and reconcile for Dollars amounts , Tons, SKF's which is pushed from BW to BPC Environment....
Hope this gave a brief overview of how to do Control reports/Audit reports between BW and BPC.
In a similar approach we did and automated the control reports for ECC vs BW for all of the SAP ECC/BW business areas which are playing an important role in Enterprise Analytics part of an Organization.
P.S : This option may not be useful if the full optimize is done quite frequently as the base cube will get restructured and the query redo would be needed.