A lack of clarity around roles and responsibilities is a common cause of project failure. A RACI matrix can help project managers address this issue.
A RACI matrix is a tool used in project management to clarify roles and responsibilities for various tasks and deliverables within a project. It stands for Responsible, Accountable, Consulted, and Informed, and helps ensure that everyone involved in the project understands their specific duties and the overall workflow.
The RACI matrix is designed to provide a clear structure for assigning roles and responsibilities, which is crucial for the successful execution of a project. Hereโs a breakdown of what each component of the RACI matrix represents:
In the context of SAP Activate for SAP S/4HANA Cloud Private Edition - New Implementation, a RACI matrix can be used to define roles and responsibilities for various tasks and deliverables. For instance, when defining the UX/UI strategy, the matrix might look like this:
For more detailed guidance on creating a RACI matrix, you can refer to the Define the UX / UI strategy task, which includes procedures and prerequisites for designing a strategy and documenting roles and responsibilities.
Additionally, the Ensure Operational Readiness task provides insights into defining and nominating leadership roles required for successful project execution, which can be supported by a RACI matrix.
For further information on creating and using a RACI matrix, you can explore the IAM - Authorization Concept Guidelines accelerator, which outlines the Identity and Access Management authorization concept and can help in defining roles and responsibilities within your project.
By using a RACI matrix, you can ensure that all team members are clear about their roles, which helps in avoiding confusion and improving project efficiency.
Based on the above understanding of RACI, the following details will help you understand how to adopt it into your SAP CPQ implementations during ongoing discussions with customers.
Here are typical stakeholder roles involved in an SAP CPQ implementation. You will need to adjust these based on your project structure:
Stakeholder Roles (Example - Customize to your specific project)
Role Abbreviation Role Description Typical Department/Team
PS | Project Sponsor (Executive Level) | Executive Management |
PM-C | Project Manager - Client Side | IT/Business PMO |
PM-P | Project Manager - Partner/Implementation Vendor | Professional Services |
BA | Business Analyst (Client Side) | Business Units (Sales, Ops) |
SA | Solution Architect (Partner/Implementation Vendor) | Professional Services |
FC-CPQ | Functional Consultant - CPQ (Partner/Implementation Vendor) | Professional Services |
TC-INT | Technical Consultant - Integration (Partner/Implementation Vendor) | Professional Services |
TC-DEV | Technical Consultant - Development (Partner/Implementation Vendor) | Professional Services |
BU-Sales | Business User - Sales Team | Sales Department |
BU-SalesOps | Business User - Sales Operations Team | Sales Operations |
BU-Product | Business User - Product Management Team | Product Management |
BU-Legal | Business User - Legal/Compliance Team | Legal/Compliance |
BU-Finance | Business User - Finance Team | Finance Department |
IT-Infra | IT Infrastructure Team | IT Infrastructure |
IT-Sec | IT Security Team | IT Security |
CM | Change Management/Training Team (Client Side) | Finance/Sales/Organizational Change |
Phase | Task/Activity | PS | PM-C | PM-P | BA | SA | FC-CPQ | TC-INT | TC-DEV | BU-Sales | BU-SalesOps | BU-Product | BU-Legal | BU-Finance | IT-Infra | IT-Sec | CM |
1. Project Preparation & Initiation | |||||||||||||||||
1.1 Project Kick-off Meeting | I | R | R | I | I | I | I | I | I | I | I | I | I | I | I | I | |
1.2 Define Project Scope & Objectives | C | R | A | R | C | C | C | C | C | C | C | C | C | C | C | C | |
1.3 Establish Project Governance & Communication Plan | C | A | R | C | C | C | C | C | I | I | I | I | I | C | C | C | |
1.4 Project Team Setup & Onboarding | I | R | A | C | C | C | C | C | I | I | I | I | I | C | C | C | |
1.5 Define Project Budget and Resources | A | R | C | C | C | C | C | C | I | I | I | I | R | C | C | I | |
1.6 Set up Project Environments (Dev, Test, Prod) | I | C | R | I | C | C | R | R | I | I | I | I | I | R | R | I | |
2. Business Blueprint & Requirements Gathering | |||||||||||||||||
2.1 Conduct Requirements Workshops | C | R | R | R | C | R | C | C | C | C | C | C | C | I | I | C | |
2.2 Document "As-Is" Business Processes | I | R | C | R | C | C | C | C | R | R | R | R | R | I | I | C | |
2.3 Define "To-Be" Business Processes and CPQ Flows | C | R | C | R | C | R | C | C | R | R | R | R | R | I | I | C | |
2.4 Gather Detailed Functional & Technical Requirements | I | R | C | R | C | R | R | R | C | C | C | C | C | C | C | C | |
2.5 Conduct Fit-Gap Analysis | I | R | R | R | A | R | R | R | C | C | C | C | C | C | C | C | |
2.6 Document Business Blueprint & Solution Design | I | R | A | R | R | R | R | R | C | C | C | C | C | C | C | C | |
2.7 Blueprint Sign-off and Approval | A | R | C | C | C | C | C | C | C | C | C | C | C | C | C | C | |
3. Realization & Configuration | |||||||||||||||||
3.1 CPQ System Configuration (Product Modeling) | I | C | R | C | C | R | I | I | C | C | R | C | C | I | I | I | |
3.2 CPQ System Configuration (Pricing & Rules) | I | C | R | C | C | R | I | I | C | R | C | C | R | I | I | I | |
3.3 CPQ System Configuration (UI & User Experience) | I | C | R | C | C | R | I | I | R | R | C | C | C | I | I | I | |
3.4 Integration Development & Configuration | I | C | R | C | C | C | A | R | I | I | I | I | I | R | R | I | |
3.5 Custom Development (if required) | I | C | R | C | C | C | C | A | I | I | I | I | I | R | R | I | |
3.6 Data Migration (Extraction, Transformation, Load) | I | C | R | C | C | C | R | R | R | R | R | R | R | R | R | I | |
3.7 Configuration & Development Reviews | I | R | R | C | A | R | R | R | C | C | C | C | C | C | C | I | |
3.8 Build Unit Test Cases and Execute Unit Testing | I | C | R | C | C | R | R | R | C | C | C | C | C | C | C | I | |
4. Testing | |||||||||||||||||
4.1 Integration Testing (End-to-End) | I | R | R | C | C | R | R | R | C | C | C | C | C | C | C | I | |
4.2 User Acceptance Testing (UAT) Planning | I | R | R | R | C | C | C | C | R | R | R | R | R | I | I | R | |
4.3 Execute User Acceptance Testing (UAT) | I | R | R | R | C | C | C | C | A | A | A | A | A | I | I | R | |
4.4 Defect Management and Resolution | I | R | R | C | C | R | R | R | C | C | C | C | C | C | C | I | |
4.5 Performance & Load Testing (if required) | I | C | R | I | C | C | R | R | I | I | I | I | I | R | R | I | |
4.6 Security Testing (if required) | I | C | R | I | C | C | C | C | I | I | I | I | I | C | A | I | |
4.7 Testing Sign-off and Approval | A | R | C | C | C | C | C | C | C | C | C | C | C | C | C | C | |
5. Deployment & Go-Live | |||||||||||||||||
5.1 Go-Live Planning & Cutover Strategy | C | R | R | C | C | C | C | C | C | C | C | C | C | C | C | R | |
5.2 Final Data Migration to Production | I | C | R | C | C | C | R | R | R | R | R | R | R | R | R | I | |
5.3 System Cutover & Go-Live Execution | I | R | A | I | C | R | R | R | I | I | I | I | I | R | R | I | |
5.4 Post Go-Live System Validation & Checks | I | R | R | R | C | R | R | R | R | R | R | R | R | R | R | I | |
5.5 User Training & Go-Live Support | I | R | R | C | C | C | C | C | R | R | R | R | R | I | I | A | |
5.6 Go-Live Communication & Stakeholder Updates | I | R | R | I | I | I | I | I | I | I | I | I | I | I | I | R | |
5.7 Go-Live Sign-off and Project Closure | A | R | R | I | I | I | I | I | I | I | I | I | I | I | I | I | |
6. Post Go-Live Support & Optimization | |||||||||||||||||
6.1 Hypercare Support & Issue Resolution | I | R | R | C | C | R | R | R | R | R | R | R | R | R | R | C | |
6.2 Performance Monitoring & Optimization | I | C | R | I | C | C | R | R | I | I | I | I | I | R | R | I | |
6.3 Ongoing System Enhancements & Change Requests | I | R | R | R | C | R | R | R | R | R | R | R | R | C | C | C | |
6.4 Knowledge Transfer & Documentation Updates | I | R | R | R | C | R | R | R | R | R | R | R | R | C | C | R | |
6.5 Project Retrospective & Lessons Learned | I | R | R | R | C | C | C | C | R | R | R | R | R | I | I | C |
By using this detailed RACI matrix as a starting point and customizing it to your specific SAP CPQ implementation project, you can establish clear roles and responsibilities, improve communication, and enhance project efficiency.
Good luck with your implementation!
Feel free to share this detailed blog with your colleagues who might need it during crucial times in the project.