Wrong delivery date - Quote Order to Sales Order

vepavani89
Explorer
0 Likes
881

Hello

We are facing some issues when sales orders are created referencing quote orders,

The deliveries are created with the wrong delivery promise date, in sales order it should be 3 days starting from  quote date creation, but it's not take on.

We had a recent migration from ECC to S/4, I checked the legacy system and all the configuration are similar in both environment 

Could you please help with this topic

Accepted Solutions (0)

Answers (3)

Answers (3)

jignesh_mehta3
Active Contributor

You mean Delivery Date in the Sales Order should be 3 days from Quotation creation. 

How is this determined? 

Was there some Development / Enhancement in ECC that is not activated in S/4? 

Thanks, 

Lakshmipathi
SAP Champion
SAP Champion
0 Likes

 in sales order it should be 3 days starting from  quote date creation

As rightly pointed out by @jignesh_mehta3 with the standard configuration, this will not happen and seems to be due to custom validation.  You need to take the help of your ABAP team to find out the root cause.

 

 

 

RobertVit
Active Contributor
0 Likes

Hi,

sounds like copy control (VOFM routine) is different after update.

Have you checked this as well?

 

Kind regards

Robert