on ā2024 Jun 18 8:45 PM
Hello
We are facing some issues when sales orders are created referencing quote orders,
The deliveries are created with the wrong delivery promise date, in sales order it should be 3 days starting from quote date creation, but it's not take on.
We had a recent migration from ECC to S/4, I checked the legacy system and all the configuration are similar in both environment
Could you please help with this topic
Request clarification before answering.
You mean Delivery Date in the Sales Order should be 3 days from Quotation creation.
How is this determined?
Was there some Development / Enhancement in ECC that is not activated in S/4?
Thanks,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in sales order it should be 3 days starting from quote date creation
As rightly pointed out by @jignesh_mehta3 with the standard configuration, this will not happen and seems to be due to custom validation. You need to take the help of your ABAP team to find out the root cause.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
sounds like copy control (VOFM routine) is different after update.
Have you checked this as well?
Kind regards
Robert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 27 | |
| 20 | |
| 20 | |
| 7 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.