on 2023 Oct 25 12:40 PM
Hi experts,
I have created a work center hierarchy which consist of 3 work centers.
A, B and C
I want to evaluate the cumulative available and required capacity.
During evaluation in CM01, in Setting —> General, I’m entering the plant and hierarchy and activating the check box for cumulation of capacity and cumulation of requirements
But capacity is not getting cumulated
Please let me know if anything is missing
Thanks