Hi Team,

Client would like to post WIP for PM orders as there is time space between GI and GR, they would like to show as WIP.

By configuring results analysis key configuration, we are able to calculate WIP, but not variance.

Could you please guide where we are missing it.

Note: It is for PM order, but not process order production order.

Regards,
Satya

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Satya,

When you are done with PM order set TECO status and re-execute WIP step and settlement step. calculated WIP is reversed from balance sheet.

Thanks,

Rau

former_member200603
Participant
0 Kudos

Hi Ratnakar,

If variance is not calculated for PM order. Is there any other way that you are aware of. Would like to capture WIP and it is to be reversed when GR is done. If GI is done, but not GR yet, the amount to be posted to some Balance Sheet Account

Regards,

Satya Yenumula

Former Member
0 Kudos

Hi Satya,

Maintenance order variance calculation is not possible.Except Production order, Process order and Product cost collectors,no variance calculation possible other type of orders in SAP.