Why i can't set MRP Area in material master?

Former Member
0 Kudos

Hi experts,

I have created my storage location as MRP area in the customizing and converted planning file entries.For some materials i can set MRP Area in MRP1 view successfully.

But there are several materials ,when i am trying to enter in the MRP 1 view in material master it is showing the following error:

error: Not possible to create; Storage location stock not included in MRP

Why?Could you give me some advise?

Regards

Joey

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Check the MRP4 view for those material codes. U may have set that Storage location stock excluded from MRP. Delete this and then try

Former Member
0 Kudos

Hi

If u got ur answer then pls give points and close the thread. If not pls comeback with the feedback/querries

Thanks & regds

Former Member
0 Kudos

Thank you Biswanath Rath ! According to your answer,i had solved the problem.

Regards

Joey

Answers (2)

Answers (2)

Former Member
0 Kudos

HI,

the system checks the Plant, Storage location and Vendor (subcontractor) fields and determines the MRP area affected according to the MRP area assignment in the material master and the settings in Customizing. The system then sets a planning file entry for the material at MRP area level in the planning file.

During this process, the system decides whether the planning file entry has to be set for just one MRP area or for all MRP areas.

Hope you will get some idea,

Thanks and regards

E.Rambabu

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Go to master data check in MRP4, for the plant and sub storge location combination....set the option = 2 MRP seperatly at storage location level??

Please check and come back.

Regards,

R.Brahmankar