on 2021 Jul 12 9:04 AM
Hello Experts,
I have created a single cycle, counter maintenance plan for any equipment, say pump, and mention scheduling indicator as to the screen below. and schedule plan for 365 days.
Annual Estimate of counter- 365
Maintenance cycle- 100 hr
I have completed the first maintenance order at 100 hrs and the order TECO was also done. The same was updated in the maintenance plan. But when I entered the next counter reading, completion counter for first call object changed from 100 hrs to 195 hrs. I am not understanding how this is happened.
Request clarification before answering.
Hello anilsoni0567,
It could be about the last confirmation on the last operation of the order.
According to the last confirmation dates it will bring the HUR from the previous date document created.
As you can read from the SAP help: "The counter reading at which the last maintenance task was carried out"
Hope that it helps.
Best Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Anil,
The short answer is that I dont know..
However, have a look at this OSS Note: https://launchpad.support.sap.com/#/notes/2275644
Otherwise I would open an OSS Message to SAP to see what they recommend..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
125 | |
9 | |
8 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.