on 2024 May 01 6:13 AM
Hi All
we have a customization in material GRN process to address the rebate process. the functionality is as below
PO is raised for 100 qty @20 - Value is 2000
GRN happens thru our custom program, it considers the quality parameters and then arrives the rate based on the material supplied. for eg: it is derived as 15
then the custom program calls the GRN bapi with the rebated value and GRN happens @15 in this scenario the value is 1500 not 2000
Now if I go to MIR7 /MIRO system creates the invoice for 2000 even my GRIR is 1500.
Is this can be restricted? please suggest
Request clarification before answering.