Which Strategy Group is OK?

0 Likes
1,703

I thinking about the answer to this question. Lots of websites provide the answer B (Planning without final assembly (50) ), but I thinking about answer D, because we have hear consumption of planned independent requirements for the semi-finished material. Please help me and explain your answer.

You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

A) Make-to-order production (20) B) Planning without final assembly (50) C) Planning with final assembly (40) D) Planning at assembly level (70)

Accepted Solutions (0)

Answers (3)

Answers (3)

Caetano
Product and Topic Expert
Product and Topic Expert

If you need to create PIRs for your semi-finished products, then you need to use strategy 70.

0 Likes

Thank You for your answer,

Caetano
Product and Topic Expert
Product and Topic Expert

Hello Natalia

You can use either planning without final assembly for your finished product or a combination of strategy 20 for the finished product and strategy 70 for the semi-finished.

I would suggest strategy 70 if you have a key semi-finished product that you need to procure in advance and your forecast is created for this specific assembly.

Otherwise, if you forecast at finished-product level, it would be easier to use a strategy like 50.

Regards,

Caetano

0 Likes

Hello Ceatano,

but question is: Which planning strategy supports the consumption of planned independent requirements for the semi-finished material and is only one answer out of four.

When I used strategy like 50, I don't see consumption of planned independent requirements for the semi-finished material. Consumption PIR is at the finished-product level, Therefore, I would reject this answer, but I preferred to make sure.

Regards,

Natalia

Dominik_Tylczynski
SAP Champion
SAP Champion

caetano.almeida I think it is a certificate question not a real life requirement.

0 Likes

Yes, exactly. Thanks 🙂

Dominik_Tylczynski
SAP Champion
SAP Champion
0 Likes

Hello natalia.wasowicz

As per SAP Help:

Best regards

Dominik Tylczynski

Hello Dominik Tylczynski

Thank You for your answer, in that case, my thinking about 70 strategy was ok.

Best Regards

Natalia