on 2019 Jul 22 10:38 PM
Hi all,
I recently started doing maintenance availability checks in mass in IW38. The material availability check works correctly, however I do no understand how SAP prioritizes PM orders when they have competing material requirements. I came up with some conclusions via trial and error.
My question is : Is this documented somewhere? I can not find the logic for this anywhere. For example, I don't know if the order priority has an impact on this, or if SAP prioritizes orders that can be completed vs orders that have multiple materials missing ....
Here's what I have so far ...
Note: I am not running MAC upon creation of the order, none of the orders have been released, and my config is set up to look at all material reservations.
CASE 1 : Orders require the exact same amount of material at the same time, orders have the same priority
EXAMPLE:
CONCLUSION: Which ever order is on top of the list when the MAC is executed will get the material confirmed to it
CASE 2 : Orders require the exact same amount of material at different dates
EXAMPLE:
CONCLUSION: Which ever order is on top of the list when the MAC is executed will get the material confirmed to it. The date does not impact the material availability check
Any help would be appreciated,
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
9 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.