Where can I find the change number used in MM12 transaction?

allen_heindel
Explorer
0 Kudos
292

I ran tcode MM12, entering a material and change number.  I made a change to the x-plant material status.  In tcode MM14 I can see the pending change, but how do I find the change number that I used?  MM14 does not show that.

View Entire Topic
Sanan
Active Participant
0 Kudos

Hi,

Did you check CDHDR table, I hope you will find it there.

Thanks,

allen_heindel
Explorer
0 Kudos
Thanks for the suggestion, but for scheduled transactions (MM12), CDHDR does not have an entry. MM14 will show me that a scheduled change exists but does not give me the change number used.