on 2010 May 19 6:18 AM
Hello Gurus
when try to create scheduling agreement with doc type LP it is not picking item category LPN , schedule line CP, instead it is picking LZN , L1 by default and giving error LPN item is not defined , but it is already there , looking for some inputs reagarding this .?
Thanks in advance
Ravi
Edited by: RAVIMSD on May 19, 2010 7:18 AM
Edited by: RAVIMSD on May 19, 2010 7:43 AM
I Cat - LPN is relevant for
Business Item
Sch line allow
Wgt/Vol relevant
Credit active
determine cost
and Incompletion Proced. 22 Sched.Agreement Item
where as
I Cat - LZN is relevant for
Business Item
Sch line allow
Item rel for Delv
Wgt/Vol relevant
determine cost
and Incompletion Proced. 34 SchedAgrItm w.DlvScd
For your error check the Item category determination for your desired I cat
ie, Sales Doc + I Cat Grp + Usage (if any) + Higher I Cat (if any) = Default I Cat, Manual I Cat.
Thanks & Regards
J Prakash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
> LP it is not picking item category LPN , schedule line CP, instead it is picking LZN , L1 by default and giving error LPN item is not defined
1. Check you desired I Cat LPN (Tcode VOV7) is there in I Cat list for Sales doc and I Cat Group maintain in your material master.
2. Check the I Cat determination for LP sales doc type, particularly for I cat for LZN with Sales doc LP.
3. If your still able to analysis the error then kindly for all entries Sales doc LP (Tcode VOV4) replace LZN DfItC as LPN and place MItCa as LZN.
Thanks & Regards
JP
Thank you all
Regards
Ravi.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
9 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.