on 2007 Jul 23 4:57 AM
Hi gurus,
I'm trying to give the WBS maintenance and the budgeting function to different people. Is there any way to control the WBS status so that whenever there is a change on budget, the WBS status is set back to UNreleased? In this way, the WBS maintenance guy is aware of any budget changes cuz without releasing the WBS, no one could post any actual value to it.
Hello
The following is a list of WBS properties:
Planning (to plan actual costs)
Account assignment (to post costs)
Billing (to post revenues)
The SAP Joint Venture Accounting (JVA) information you specify at the project level is applied to all WBS elements within the project, as you set them up. You must assign all WBS elements to a project. Therefore, you must set up the project before attempting to set up a WBS element. In order to set up a project, you must assign it to a project profile. The profile should be set up as a part of SAP CO configuration.
Check the settings
On the SAP Easy Access menu, choose Joint venture accounting ® Master data ® Projects/AFEs ® Project builder.
Procedure
1. Enter the WBS element on the Change Project: Initial Screen.
2. Choose from the following function keys to access the several change screens:
Function
Screen Name
Structure
Change Project: WBS Elements - Descriptions
Person respons
Change Project: WBS Elements - People Responsible
User status
Change Project: WBS Elements - User Status
System status
Change Project: WBS Elements - System Status
Proj.definition
Change Project: Project definition Basic Data
Reg
*assign points if useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
8 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.