on 2023 Oct 30 9:38 AM
Hi Experts,
I have the following two queries on WBS Cost Center and Auc Cost Center in Public Cloud:
1. In Public Cloud the Responsible Cost Center is a mandatory field for Project/WBS Element. When the Processing status is set to "Release" in Project Control- Enterprise Projects app, for the Project/WBS Element with investment profile the AuC is generated successfully and when the AuC master data is validated in the Manage Fixed Assets App, the cost center is not populated.
When I checked in the on-Prem environment, if either the Responsible or Requesting cost center is maintained at the WBS element Basic Data, the AuC cost center field value is getting populated(preference to Requesting CC).
2. And the Investment Measure-AuC is editable from CJ20N or AS02(No postings) whereas in Cloud the time Dependent fields are not editable.
Is this standard behavior in the Public Cloud?
Request clarification before answering.
Hi Sumanth,
When the investment project is released the AUC is created. Postings are made the project and later setted to the AUC, for AUC there is no need to assign the CC/WBS element as the costs are already posted to the project, and associated the the CC assigned there.
Regards
Mark
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
15 | |
8 | |
7 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.