We will have to return the defect material back to the vendor for which we create a Return PO. We are moving the material from unrestricted to Block and transferring the blocked stock to WBS element (Project Stock). WBS flowing into Material document. The issue is WBS element is NOT flowing into Accounting Document, all I see a number in the filed “Assignment” and WBS field is EMPTY. What could be the reason?