on 2015 May 26 4:46 PM
Dear Gurus,
I'm posting this after thoroughly going all the related posts. But none has the answer.
I'm experiencing the problem as described in the SAP note: 0000159850.
I'm trying to settle the costs in WBS to AuC asset which should be auto generated during first settlement rule. But the problem is, the system is checking for the available budget in upper level WBS while settling and since there is no available budget in the upper level(as it's already distributed to the bottom, the one which I'm trying to settle) it's showing the 'Budget not available error'. There are several solutions here as described below.
My solution of interest is point 3 above. Is it possible to use 'direct settlement' option for settlement to AuC? Does anybody know how we can decide whether the settlement via CJ88 is 'direct settlement' or 'multilevel settlement'?
Please help me out.
Cheers,
Mahesh
Request clarification before answering.
Hi Mahesh,
Just for my understanding.
As per your issue, you are trying to settle cost from WBS to AuC, but in the sap note 0000159850, it was settling cost within project between WBS element. I feel both are different.
Can you confirm the same ?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Maria,
You are right! I'm trying to settle cost from WBS to AuC. And during the process it's checking for remaining budget. If I exempt the cost element(of the AuC asset class) from availability control, I get no error. One more trouble I'm facing is that even in that case the settlement to AuC is deducting the available budget in the WBS.
Thanks,
Mahesh
Dear Maria,
Thanks for your quick reply. I understand the issue better now. While settling it's checking for the remaining available budget in the same WBS itself(not the upper ones).
So I added the AuC cost element to exempted list and is able to settle the cost without any warning or error, BUT now I can see that the 'Actual ' in the WBS is just doubled and it's deducting the remaining budget in the WBS!
For e.g.in the WBS
1. Actual values before settlement = 90,000 USD
2. Actual values after settlement to AuC = 180,000 USD ==> The settlement cost element is deducting the remaining budget
3. Actual values after capitalization of asset = 90,000 USD.
Please see the reports for step 2 symptom
SAP Note 51971 describes this symptom also:
In the active availability control, settled values are taken into account twice, or not at all.
But I'm unable to understand the solution described there!.
Thanks in advance.
Regards,
Mahesh
Dear Maria,
The error is the normal Budget availability control error.. Budget exceeded.. Sorry I dont have the screenshot now.
However I found something in thread
ACSET now:
Now after settlement to AuC, the report is dislayed correctly.
BUT now, after capitalization, in the budget reports, the actuals are cleared(0) that means it shows like the whole budget is now available
Could you help?
Thanks,
Mahesh
Hi Mahesh,
Hopefully, this seems to be the issue. Remove the PSPNR assignment with * in ACSET .
Below is the OSS note. Check it whether this relates to your issue.
1935079 - Error message BP604 budget exceeded during settlement
Regards
Terence
Dear,
Did you activated your budget "Over all" or "Annual" in your settings in "Availability control activation types" ?
What is your "Activation type" in "Availability control activation types" ?
If you assign "Over all " here system will check budget against "Over all Budget" values only.
Could you kindly check these parameters in your "Budget profile" assigned to this project?
Regards,
Pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
In this case system will only check budget against "Over all Budget" values only.So do you sufficient budget for that Project over all?
If you have enough budget but still getting error ,Then just run transaction CJEN and then CJBN to restructure the Budget.Did you try this.
Regards,
Pardhu
Dear,
Kindly check the reports RKANBU01 which will update PR/PO commitments for this project.
and then run report RKACOR04 which will update entries in table like COSP, COSS,COEP, COOI.
and then run CJEN AND CJBN
Note 152571 - Composite SAP note: Missing or incorrect commitments.Hope this may help you little bit.
https://service.sap.com/sap/support/notes/152571
Regards,
Pardhu