cancel
Showing results for 
Search instead for 
Did you mean: 

Very Strange: SET UP time is not calculated Automatically Even for standar

Former Member
0 Kudos

Hi Teams,

I came across with one of the stange issue.

We have define a Setup , Machine & labour activity in a workcenter .

Set Up formula ( use Standard ) = SAP_01 * SAP _11

& same std use formulae used for Machine aws Labour

Now when we do a confirmation / Post activity in MFBF for a certain FG quantity. Machine & Labour activity planned time automatically extract *but only , Set up activity value is not extracted as per the plan. *

I have each & every combination & setting Like change parameter ,change standard value key in WC .....

but problem is not being identified .

Same is found for the production order also.

Could you please let me know if anybody face such kind of issue in past.

Many thanks & Regards

Neeraj

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi

Check whether u have defined the set up time relevant for costing or not. if not click relevant costing in routing.

After that did u mention the variable cost and fixed cost for each activity type in customization? if not go to spro and search for activity types and open them in costing and give the cost of each activity.

Nanduri

former_member189817
Active Contributor
0 Kudos

Hi,

pls check the following,

1. Is setup activity is extemded for this month for that particular cost center in KP26?

2.Is Routing contains valid setup time?

3.Check CR02 contains valid activity for setup?

Former Member
0 Kudos

Hi ,

Thanks for ur's update !

Do you mean to say that system will not propose the setup time when we do a confirmation in the repetitative Manufacturing even though we have made a setup in WC using Standard Value key.

Same in production order confirmation too..

Please suggest

Many thanks

Neeraj

Former Member
0 Kudos

Hi,

Repetitive Manufacturing used for production for large quantities.

In this no setup time include.

So why are you assigning setup time in routing.

In work center assign SAP3 as a Standard value key.

In this only Machine time & Base qty are assigned.

Scheduling & Capacity formula is different for REM. In this no setup time included.

Create Rate routing by CA21 for REM instead of CA01.

Regards,

Dharma

former_member184655
Active Contributor
0 Kudos

Dear Neeraj,

In REM scenario ,setup time is not included as it will not be planned one.

Can you tell me what's your expectation from activity posting and from MFBF.

Regards

Mangalraj.S

Former Member
0 Kudos

Hi,

Do u mean to say, Set up time is not calculated based on planned qty, like machine time & labor time.

Setup time is required to setup the machine initially to carry out operation.(For First Piece alone).

So system will not increase the setup time based on planned qty .

Please letus know why do u want to calculate setup time based on plan.

Regards

pardeep