on 2008 Sep 22 11:30 AM
Hi friends,
Is there any difference between creation of BOM,Routing,production order for configurated material and other materials. if yes kindly guide for this.
Regards,
Renu...
Routing is nothing but your Process Plan
Explain the step how to create routing?
By : Vishal Patil
You have to proceeds following steps:
1) CA01 - Create routing
First screen = Material on which you have to create a routing
Plant
Second screen = Usage 1 if you create routing for production purpose.
Status 4 release general
Enter
2) Now go on to application tool bar and select operation
Here you have to enter work center, control key and description
For eg. w/c 1 plant pp01 description
w/c 2 plant pp01 description
plant pp99 goods reciepts
3) Now select the component allocation
Select the material here and click on to the new assignemnt for assign the operation seqence on to the material.
4) SAVE
Now routing is create with routing group number .
BOM - Bill of material
How to Create a Simple BOM?
Transaction code : CS01
Material : Your Material code
Plant : Your Plant
BOM Usage : 1
Item Category Componment Quantity
0010 L Your Material code Your required quantity
Save your entries
You can used CS02 to changed the BOM and CS03 to display the BOM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.