on 2024 Oct 11 6:12 PM
I have a configurable material with strategy 25, working as expected in sales order.
I need to have MTS for the same material code.
So far, I have tried:
1. strategy 56 and 89 in configurable materials.
2. Strategy 70 and 40 in variants
3. Routing is created, PV is there, Production BOM have 3 configurations and 2 static BOM items
4. Cross customizing in MRP 3 (Configurable material and variant and planned variant)
5. requirement generated through safety stock and Forecasting
6. Maintained Quota
7. Maintained configuration probability in MD61
So far, I have not yet succeed in creating requirement with MTS. I have searched posts related to MTS, applied the same, read SAP config and maintenance instructions.
CU50 showing no errors, config working fine with sales order, I can conclude the config is working as expected with sales order.
Details I have maintained in Material Master:
1. FG Material :
Procurement type : E
Strategy 56 / 89
Assigned class 300
2. RM :
Procurement type : F
strategy : 40 , 70 , blank
Request clarification before answering.