on 2022 Nov 02 5:19 AM
Hi all,
I have process of milestone billing.
1. Create wbs elements with milestones cj20n
2. Create sales value contract
3 Complete the milestone through cj20n
4 bill that particular milestone with reference of sales value contract.
This is process which we have configured but in this process Value Released field is not updating.
I have created sales value contract of 1000$ and billed 200$ but in value released field, It is showing 00

Request clarification before answering.
Hello ,
I am getting same issue , could you please share if any solution was suggested
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is the item category of contract has "E" for Completion rule ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 22 | |
| 15 | |
| 14 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.